We’ve hit the ground running for 2026. Civil works on-site have progressed rapidly, with the final elements now nearing completion. Roads are in, paths are done, and the site is being readied for Ultima’s first homes.
February 2026 Construction Update
What’s happening now?
- Water meter installation is underway
- Final concrete works to the driveway and footpath easement are underway
- Site cleaning works will begin in preparation for handover

What’s complete?
- All site clearing, earthworks, retaining walls and stormwater works are finished.
- Kerbs, channels, pavements, driveways, and the carpark are complete.
What’s next at Ultima?
Construction of the first townhomes at Ultima will commence in March 2026.
We’ll share progress from the site on our website, our social media channels, and in our regular email communications.
Stage 3 is coming soon, so make sure you’re subscribed to our email newsletters to hear about it first.