December 2025 Construction Update

As the year comes to an end, progress at Ultima continues to hit every forecasted milestone. The community is beginning to take shape at ground level, and excitement is building onsite. 

 

Here’s what’s been happening at Ultima

 

What’s happening now?

 

  • Cable pulling in Stage 4 is underway, while all other stages have now been completed.
  • Easement works are underway, with traffic controls in place.
  • Seal and asphalt laying works are nearing the halfway mark
  • Watermain, pump station and sewer works are at 95% completion
  • Final topsoiling is underway.

 

 

What’s complete?

  • Earthworks, retaining walls and stormwater works are finished.
  • Kerbs and channels are complete.
  • Driveways and carparks are complete.

 

 